The current highway Suedlink to the wind, connect the wheels to the North with the industrial South. Now, network operators have proposed the route – you are likely to encounter resistance.
The operators have submitted to the exact course of the Central electricity highway by Germany. The high tension road to transport wind power from the mouth of the Elbe to Bavaria and Baden-Württemberg. The intention of the policy, you should be in 2025 finished.
But on the schedule there is already considerable doubt. “This is an extremely ambitious goal,” said Christoph Schulze-Wischeler, head of grid development at Tennet. For this, everything should run smoothly with maximum acceleration and no complaints. This is, however, unlikely.