The construction Implenia together with the Frutiger AG, and the Ghelma AG Baubetriebe of the kraftwerke Oberhasli (KWO), the order for the construction of a dam in the Bernese Oberland. The lead lies with the Frutiger AG.

Implenia was involved with 42.5 percent of the ARGE Grimsel, the largest Swiss construction company on Monday. The volume of the order spent a total of nearly 100 million Swiss francs.

The existing dam hospital lamb dates back to the year 1932, and the approximately 90-year-old dam is now to be replaced. The new double-curved arch dam will drawn up immediately in front of the existing wall. The new structure offer the possibility to be able in a later Phase to expand the Grimsel reservoir. The height of the wall is reported to be 113 meters. The old dam wall will remain. The construction works will start in summer of 2019 and will last until 2025. (Dec/sda)

Created: 25.03.2019, 08:10 PM